HIGHLIGHT PROJECTS

       Notable Pipeline Projects

  • District Cooling System & Power Plant Co., Ltd. 
    Natural Gas Pipeline 
  • TLP Cogeneration Co., Ltd.
    Interconnecting Natural Gas Pipeline 
  • PTT PLC.
    Natural Gas Pipeline
  • Amata Corporation at Amata City Industrial Estate
    Reroute Gas Pipeline diameter of 28”
  • Kangwal Textile Co., Ltd.
    Natural Gas Distribution Pipeline
  • Thai Tank Terminal Ltd. 
    Phenol and Acetone Pipeline
  • PTT PLC. 
    MTP Interconnecting Natural Gas Pipeline
  • PTT Plc.
    BV#9 Modification Project

 

      Notable Process & Industrial Plant Projects

  • Samsung Engineering at PTT Gas Separation Plant No. 5 
    Fabrication and Erection of a 4,000 ton Steel Structure
  • GE Toshiba Silicones (Thailand) Ltd. 
    C1 & C2 Rework System of Silicone Plant

 

Bio-Diesel Plant Project
Client
 : Bangchack Bio Fuel Co., Ltd.
Contract Value : 757 million Baht
Construction Period : March 2008 - June 2009
Type of Contract : EPC Contract
Project Description : EPC turnkey construction of bio-diesel power plant (at approximate plant capacity of 300,000 liters per day) by production technology from Europe

Prasae Water Transmittal Pipeline Project
Client :
 Royal Irrigation Department
Contract Value : 
1,200 million Baht (US$34.3 million)
Construction Period :
 May 2005 – May 2007
Type of Contract : 
Construction of water transmitting pipeline
Project Description : Installation of a water transmitting pipeline (diameters of 900, 1,200, 1,400 and 1,600 mm.) in Ampur Wangchan, Rayong Province; a total distance of 20 kilometers.

Wang Noi-Kaeng Khoi Gas Pipeline Project
Client :
 PTT Public Company Limited
Contract Value : 
2,100 million Baht (US$60 million)
Construction Period : 
July 2005 – October 2006
Type of Contract : EPC Contract
Project Description :  Installation of a 36 inch diameter gas pipeline from a power electric plant in Ampur Wang Noi, Ayudhaya Province, to the Gulf Electric Co., Ltd.’ s plant in Ampur Kaeng Khoi, Saraburi Province; a total distance of 72 kilometers.

WS Recovery Boiler Project
Client :
 Thai Incinerate Service Company Limited
Contract Value :
 515 million Baht (US$14.7 million)
Construction Period :
 February 2005 – November 2006
Type of Contract :
 EPC Contract
Project Description : Installation of a WS Recovery Boiler Unit* in the Caprolactam/ Ammonium Sulphate Complex owned by Thai Caprolactam Public Company Limited (TCL) located at the ThaiPetrochemical Industrial Estate in Rayong

Knock Out Drum Phase II Project
Client 
: PTT Public Company Limited 
Contract Value : 126.5 million Baht (US$3.6 million)
Construction Period : July 2005 – March 2006
Type of Contract : EPC Contract
Project Description : Engineering, procurement and construction of a 0.95 kilometer Pipeline with diameters of 24, 30 & 36 inches. Natural gas from a new knock-out drum is sent through piping anda control valve system to the Gas Separation Plant and Mercury Removal Unit.